148 Chester Court              Bowling Green, KY  42103                                         Phone - (270) 843-2247           Fax - (270) 843-9323
  750 West 15th Street         Hopkinsville, KY 42240                                              Phone - (270) 885-9893           Fax - (270) 885-9869

 

 15th Avenue Realignment and Construction Management - Western Kentucky University:

For a number of years, the intersection of 15th Avenue with Big Red Way had been a dangerous intersection due to a sharp curve and steep grades. Numerous accidents had occurred at this intersection and Western Kentucky University recognized the need to increase safety for students, pedestrians and the traveling public. As a result, Western Kentucky University retained DDS ENGINEERING, PLLC to design the reconstruction of the 15th Avenue intersection with Big Red Way. Once the plans were approved, bids received, and a contractor hired, DDS ENGINEERING, PLLC was contracted to provide construction management services for the University. Western Kentucky University felt that having the engineer of record for the design of the project also perform the construction management provided a distinct advantage since we were already familiar with the site, design, and objectives for the project. We began our construction management of the project with the review of shop drawings and cut sheets submitted by the contractor. We were also provided with a construction schedule so that we could monitor and report the contractor's progress to the owner. Since this project occurred at the same time as the installation of utility relocation work along the new 14th Avenue, we were able to coordinate the construction management of both projects. This arrangement helped the owner coordinate the two projects and saved the owner time and money by not having two construction managers for two projects that were adjacent in the field. The time frame for this project was very critical as the roadway had to be opened before students returned to campus.

DDS ENGINEERING, PLLC had an observer on site every day that the contractor had crews working on site. Our observer documented the daily progress of the installation of the storm sewer system and the roadway itself. We also served as a liaison between the contractor and the owner and answered several questions from the contractor. This communication kept the project moving and on schedule even though several issues were found during construction that were not anticipated. Despite the unanticipated problems, the project was completed on time and provided vehicular access to the returning students. We also provided punch list items to the owner at the time of substantial completion and at the time of final completion.




-
Photos:.

All Content Copyright 2006-2010 DDS ENGINEERING, PLLC